Distribution transformer health monitor
Distribution transformers fail from overload and overheating, cutting power to whole streets for days. A monitor that tracks load current, voltage, oil temperature and oil level and alerts the utility early can prevent many failures.
- Parts
- ₹4,140
- Build
- 14 weeks
- Board
- ESP32
- Objectives
- 5
Block diagram
- CT sensorMeasures load current
- Voltage sensorMeasures secondary voltage
- Oil temperature probeMeasures top-oil temperature
- Oil level floatDetects a leak
- ESP32Works out load and hot-spot risk
- 4G or Wi-Fi alertTells the utility
- Cooling fan relayStarts forced cooling
- 4G modemSends SMS alerts and calls over the mobile network+
Objectives
- To measure load current, voltage and percent loading against the rating.
- To measure top-oil temperature and estimate hot-spot rise.
- To start cooling and raise an alert on overload, high temperature or low oil.
- To log a day of readings on the test transformer.
- To send SMS alerts through a 4G modem where no Wi-Fi is available.
Parts and specifications
- ESP32 DevKit V1Dual-core 240 MHz, 520 KB SRAM, Wi-Fi + Bluetooth, 3.3 V logic, 12-bit ADC (use ADC1 pins when Wi-Fi is on)₹450Buy
- SCT-013-030 split-core CT0 to 30 A AC to 0 to 1 V AC (built-in burden), clamp on without breaking the wire₹450Buy
- ZMPT101B AC voltage sensorIsolating voltage transformer up to 250 V AC, analog output centred at VCC/2, trimmer for gain₹180Buy
- DS18B20 waterproof probe−55 to 125 °C, ±0.5 °C from −10 to 85 °C, 9 to 12-bit, 1-Wire with 4.7 kΩ pull-up, 750 ms at 12-bit₹240Buy
- Vertical float switchReed switch in a float, 10 W 100 V DC max, use as a dry-run or full-tank limit₹120Buy
- 5 V relay module (1 channel)10 A 250 V AC contacts, coil 70 to 80 mA, optocoupled input; many trigger at 3.3 V, check yours₹70Buy
- Small 230/12 V 2 A transformer as the test unit, with a load₹450
- Box, fuse and terminal strip₹250
- A7670C 4G LTE module4G Cat-1 with 2G fallback, SMS, calls and data, works with any Indian SIM including Jio; 3.4 to 4.2 V, 2 A peaks₹1,500Buy
- LM2596 buck converter (set to 4.0 V for the modem)4 to 40 V in, 1.25 to 37 V out, up to 2 A continuous (3 A peak), about 85% efficient₹90Buy
Total about ₹4,140 at typical online prices. Tap a part for its pinout and datasheet notes.
Design calculations
Rated secondary current of the test unit 2 A. Measured 1.7 A RMS → 85% load.
Sample at 2 kHz for 200 ms (10 cycles): Irms = √(Σi² / N). It handles distorted current from electronic loads.
Hot spot ≈ top oil + H × gr × K^y. With top oil 70 °C, H = 1.3, gr = 23 K, K = 0.85, y = 1.6: 70 + 1.3 × 23 × 0.77 ≈ 93 °C.
Insulation ageing roughly doubles for each 6 °C above 98 °C hot spot, so short overloads matter less than long ones.
Pin map
| Signal | Pin or connection |
|---|---|
| SCT-013 (biased at 1.65 V) | GPIO 34 |
| ZMPT101B OUT | GPIO 35 |
| DS18B20 probes (top oil, ambient) | GPIO 4 |
| Oil level float | GPIO 27 (pull-up) |
| Fan relay | GPIO 26 |
| OLED | GPIO 21 / 22 |
Firmware outline
- Every 10 s compute Irms and Vrms from 10 cycles of samples.
- Read top-oil and ambient temperatures every minute.
- Compute load %, hot-spot estimate and a health state.
- Start the fan above 80% load or 65 °C; alert at 110% load, 85 °C, or low oil.
- Send readings to the dashboard; keep a 24 h log.
Test plan
| Test | Expected result |
|---|---|
| Load stepped 25, 50, 75, 100% | Current vs clamp meter within 3% |
| Supply voltage via variac (with guide) | Voltage tracks within 2% |
| Probe warmed in hot water | Fan starts, then alert |
| Float lifted | Low-oil alert |
These rows start your results table when you plan the project.
Viva practice
Say your answer out loud first, then check. The first 2 answers are free; Maker opens all 5.
Make it yours
One or two upgrades for a mini project, two to four for a major one.
Build these first
Datasheets and sources to cite
- IS 2026 (power transformers)
- IEC 60076-7 loading guide for oil-immersed transformers
- YHDC SCT-013 datasheet
About this project
How much does the distribution transformer health monitor project cost?
About ₹2,550 for the parts in the base list: ESP32 DevKit V1, SCT-013-030 split-core CT, ZMPT101B AC voltage sensor, DS18B20 waterproof probe × 2, Vertical float switch, 5 V relay module (1 channel), 12 V DC fan 80 mm, 0.96 inch OLED (SSD1306, I²C), Small 230/12 V 2 A transformer as the test unit, with a load, Box, fuse and terminal strip.
How long does it take?
About 12 weeks for the base project, built on an ESP32. Each upgrade adds time.
Which branches is it suitable for?
Electrical and Electronics, Instrumentation, Electronics and Communication, as a major project.
Which pins and design calculations does it use?
SCT-013 (biased at 1.65 V) on GPIO 34; ZMPT101B OUT on GPIO 35; DS18B20 probes (top oil, ambient) on GPIO 4. Worked calculations on this page: percent loading, true rms, hot-spot estimate (iec 60076-7 style), ageing.
How do I test it?
Load stepped 25, 50, 75, 100%: Current vs clamp meter within 3%. Supply voltage via variac (with guide): Voltage tracks within 2%. Probe warmed in hot water: Fan starts, then alert. Float lifted: Low-oil alert.
What are the objectives?
To measure load current, voltage and percent loading against the rating. To measure top-oil temperature and estimate hot-spot rise. To start cooling and raise an alert on overload, high temperature or low oil. To log a day of readings on the test transformer.